110 kV auxiliary power supply to opencast mining operations
Start / Referenzen / 110 kV auxiliary power supply to opencast mining operations
Overview
Customer
Lausitz Energie Kraftwerke AG
Location
Germany 02943 Boxberg
Duration
2013 - 2016
LEAG (Vattenfall) operates several power plants and opencast mines in the Lusatia region. Within the scope of this project, direct feeders from the Jänschwalde and Nochten/ Reichwalde power plants to the opencast mines, via the 110 kV grid, were established. This enables supply from the auxiliary service supply systems of the power plants and improves base load utilization of the power plants.
Services of VPC at a glance
Feasibility studies with economic appraisal to determine the optimal concept
Preparation of building application
Drawing up tender documents
Bid evaluation and support during contract negotiations
Basic engineering and network calculation
Review of drawings and release of documents for execution
Site supervision
Provision of construction and commissioning management personnel