Engineering services at the Reuter West CHP Power Plant
Start / Referenzen / Engineering services at the Reuter West CHP Power Plant
Overview
Customer
Vattenfall Wärme Berlin AG
Location
Germany 13599 Berlin
Duration
01/2000 - today
The Reuter WestCombined Heat and Power Plant is located in the Siemensstadtdistrict of Berlin. The two 300 MW units were commissioned in 1987 and 1988/89, respectively. The Reuter West CHP Power Plant is Berlin’s most powerful power plant. A VPC project team firmly established at the site has been providing engineering services year after year for the operation, maintenance and integration of new projects. In addition, the VPC colleagues ensure documentation management at the site. Using the CAD software COMOS PT, not just documentation management but also engineering for the electrical and I&C engineering, process engineering, mechanical engineering and civil construction disciplines is provided.
Services of VPC at a glance
Administration of the COMOS documentation management and plant engineering system
Management of data for lists, e.g. lists of motors, consumers, valves and vessels
Programming of process software in the control system INVENSYS
Hardware and software planning, allocation of KKS identification codes
Compiling and management of technical documentation, such as PIDs, operating manuals, safety reports
Performance of engineering tasks in the fields of electrical engineering, I&C, process engineering, mechanical engineering, civil construction
Construction supervision, site management, commissioning