Report
Project

Spectacular tariffs received from the solid bidders for Phase 1 of Uzbekistan project in Sherabad.

Masdar (Abu Dhabi Future Energy Company) has managed to achieve the lowest tariff of 1.8045 $c/kWh for the 457MWac PV plant including a new 220/110/10kV substation + 52km double circuit transmission line for grid connection.

Suntrace is proud to have supported Asian Development Bank (ADB) as Technical Advisor in the tender process and continues to provide assistance for Phase 2 of the project.